Line efficiency from SMV: how to calculate it, and how not to

Efficiency is the most quoted number on a sewing floor and one of the most often miscalculated. Here is the standard formula, and the mistakes that distort it.

By the BunonBrain team · · 6 min read

Ask ten supervisors how efficient their line was yesterday and you may get ten different methods. Some divide output by target, some include helpers and some don't, some use clock hours and others available minutes. The result is a number that can't be compared between lines, let alone between factories.

The standard formula

Line efficiency compares the work the line produced, measured in standard minutes, with the minutes the line had available.

Efficiency % = (Pieces produced × SMV) ÷ (Operators × Minutes worked) × 100

SMV: standard minute value of the garment, from a time study or a recognised database.

A line of 40 operators working a 480-minute shift has 19,200 available minutes. If it sews 900 shirts with an SMV of 14, it produced 12,600 standard minutes, an efficiency of 65.6%.

Five common mistakes

  1. Using target instead of SMV. Output ÷ target measures plan attainment, not efficiency. If the target was set loosely, the line looks efficient when it isn't.
  2. Leaving people out of the denominator. Helpers, ironers and feeders on the line consume minutes. Decide once who counts and apply it everywhere.
  3. Ignoring overtime. Minutes worked must include overtime, or the evening hours inflate the result.
  4. Mixing styles without weighting. When a line changes style mid-day, multiply each style's output by its own SMV before adding.
  5. Subtracting downtime silently. Machine breakdowns and waiting for bundles are real losses. Report them as non-productive time rather than removing them from the minutes.

Why consistency matters more than precision

An efficiency figure is only useful if the same method is used every day, on every line. A consistent number shows trends and differences between lines; an inconsistent one starts arguments.

In BunonBrain, efficiency is calculated from recorded output, the style's SMV and the minutes available in the line's shifts. Nothing is typed in or estimated.